This stage consists of three units(Unit-1, Unit-2, Unit-3) each with a generation capacity of 200MW. The turbines for these three units were manufactured by The Ansaldo Energia Ltd. The construction began in the late 1970s and these units have performed well over a long period setting many records regarding maintenance and generation over the other two stages.

Civil mantanencr


 Once in two years, these units are stopped and overhauled, one unit at a
 time. The overhauls are usually taken up during the months June to 
September as the monsoons activate hydel power generation which 
substitute the power generation lost due to the overhaul of the unit. The
 same practice is followed allthrough the country. The overhauls usually
 take 15 to 20 days per unit  provided there is no major repair involved.
 Major repairs include turbine casing,turbine rotor damage and other
 damages that require transporting the equipment to another location(usually the 
manifacturer). The overhauls are the dissipators of the annual PLF of 
any power plant.
 